| Lump-sum Cost Calculation of Private Sewer Facility |
Version 5A |
10/25/2004 |
|
|
|
|
|
|
|
|
|
|
| Facility Cost (Paid up
front to vendor ) |
|
|
|
|
|
|
| Estimated Cost New Private
Facility |
250,000 |
|
|
| Additional (legal, consulting, hauling
etc) |
25,000 |
|
|
|
Total facility cost requiring up-front financing |
275,000 |
|
|
|
For each 1.79% unit |
4,923 |
|
|
|
For each 2.86% unit |
7,865 |
|
|
|
For each 1.34% unit |
3,685 |
|
|
|
|
|
| Base Year Operating Cost
Assumptions |
|
|
|
|
|
|
| Estimated
Annual Sewage Plant Operating
Budget for 2005 |
|
|
|
| Expected 2005
private facility electricity cost |
4,000 |
|
|
| Expected 2005
Sewage plant operating contract |
36,000 |
|
|
| Expected 2005
Sewage plant maintenance cost |
6,000 |
|
|
| Expected 2005
Supplies |
4,000 |
|
|
|
Total sewage plant operating budget for 2005 |
50,000 |
|
|
|
For each 1.79% unit |
895 |
|
|
|
For each 2.86% unit |
1,430 |
|
|
|
For each 1.34% unit |
670 |
|
|
|
|
|
| Projected Operating Costs
Over Life of Plant (Included in condo fee) |
|
|
|
|
|
|
| Assumptions: |
|
|
|
| Annual Increase in Sewage Plant
Operating Cost |
0.03 |
|
|
| Life of new facility in years (n) |
30 |
|
|
| Total outlay over 30years |
2,581,134 |
|
|
| NPV discount rate"r"(http://www.cbo.gov/showdoc.cfm?index=3983&sequence=5) |
0.035 |
|
|
| Computation: |
|
|
|
| NPV of "30" increasing payments discounted @
"3.5"% |
1,449,275 |
|
|
|
For each 1.79% unit |
25,942 |
|
|
|
For each 2.86% unit |
41,449 |
|
|
|
For each 1.34% unit |
19,420 |
|
|
|
|
|
| Replacement Reserve
(Included in condo fee) |
|
|
|
|
|
|
| Assumptions: |
|
|
|
| Replacement Horizon (Years) |
30 |
|
|
| Original cost of facility |
250,000 |
|
|
| Expected annual increase in
replacement cost |
0.015 |
|
|
| Expected annual return on
accumulated reserve(See WSJ 10/18/04 p. C-2) |
0.04 |
|
|
| Discount rate to use in PV
calculation |
0.04 |
|
|
| Computation: |
|
|
|
| Replacement Cost=Original cost+
annual increase over30yr life
of plant |
390,770 |
|
|
| Annual required
replacement set-aside (PMT) |
6,967 |
|
|
| PV of stream of "30" equal annual set asides
discounted @ 4
% |
120,482 |
|
|
|
For each 1.79% unit |
2,157 |
|
|
|
For each 2.86% unit |
3,446 |
|
|
|
For each 1.34% unit |
1,614 |
|
|
|
|
|
| Summary: Lump-sum cost of
private facility option |
|
|
|
|
|
|
| Total
lump-sum cost of installing new private facility |
275,000 |
|
|
| Total lump-sum cost of operating
private facility over 30 years |
1,449,275 |
|
|
| Total lump-sum cost of replacing
private facility after 30 years |
120,482 |
|
|
|
Total lump-sum cost of building, operating & replacing private
facility |
1,844,757 |
|
|
|
For each 1.79% unit |
33,021 |
|
|
|
For each 2.86% unit |
52,760 |
|
|
|
For each 1.34% unit |
24,720 |
|
|
|
|
|
| Compare to lump-sum cost
of county sewer pumping station |
|
|
|
|
|
|
| DL share of county owned &
operated pumping station |
748,000 |
|
|
| NPV
of sewage fee of $3600/yr increasing @ 0.5% /yr for 30 years@4% |
66,026 |
|
|
|
Total lump-sum cost of DL contribution + stream of sewage fees |
814,026 |
|
|
|
(Note: The $814,026 lump-sum does not include the $3,000/unit |
|
|
|
|
hook-on fee which is added to each unit below) |
168,000 |
|
|
|
|
|
|
|
Public |
Vs. Private |
|
|
|
For each 1.79% unit |
14,571 |
|
|
|
After adding $3000 per unit Hook-on fee |
17,571 |
33,021 |
|
|
|
|
|
|
For each 2.86% unit |
23,281 |
|
|
|
After adding $3000 per unitHook-on fee |
26,281 |
52,760 |
|
|
|
|
|
|
For each 1.34% unit |
10,908 |
|
|
|
After adding $3000 per unitHook-on fee |
13,908 |
24,720 |
|
|
|
|
|
| The
following material is provided for those who want to dig into the numbers
and assumptions |
|
|
| Year |
Operating Cost |
Sewage Fee |
|
|
|
|
|
|
| 1 |
-50,000 |
3,600 |
|
|
| 2 |
-51,750 |
3,618 |
|
|
|
| 3 |
-53,561 |
3,636 |
|
|
|
| 4 |
-55,436 |
3,654 |
|
|
|
| 5 |
-57,376 |
3,673 |
|
|
|
| 6 |
-59,384 |
3,691 |
|
|
|
| 7 |
-61,463 |
3,709 |
|
|
|
| 8 |
-63,614 |
3,728 |
|
|
|
| 9 |
-65,840 |
3,747 |
|
|
|
| 10 |
-68,145 |
3,765 |
|
|
|
| 11 |
-70,530 |
3,784 |
|
|
|
| 12 |
-72,998 |
3,803 |
|
|
|
| 13 |
-75,553 |
3,822 |
|
|
|
| 14 |
-78,198 |
3,841 |
|
|
|
| 15 |
-80,935 |
3,860 |
|
|
|
| 16 |
-83,767 |
3,880 |
|
|
|
| 17 |
-86,699 |
3,899 |
|
|
|
| 18 |
-89,734 |
3,919 |
|
|
|
| 19 |
-92,874 |
3,938 |
|
|
|
| 20 |
-96,125 |
3,958 |
|
|
|
| 21 |
-99,489 |
3,978 |
|
|
|
| 22 |
-102,972 |
3,998 |
|
|
|
| 23 |
-106,576 |
4,017 |
|
|
|
| 24 |
-110,306 |
4,038 |
|
|
|
| 25 |
-114,166 |
4,058 |
|
|
|
| 26 |
-118,162 |
4,078 |
|
|
|
| 27 |
-122,298 |
4,098 |
|
|
|
| 28 |
-126,578 |
4,119 |
|
|
|
| 29 |
-131,009 |
4,140 |
|
|
|
| 30 |
-135,594 |
4,160 |
|
|
|
|
|
|
|
| http://www.cbo.gov/showdoc.cfm?index=3983&sequence=5 |
|
|
|
|
|
| Financing |
|
|
|
| In consultation with a half-dozen experts from the water and
municipal bond |
|
|
| industries, CBO derived
pairs of assumptions about future interest rates, |
|
|
|
| borrowing terms, and the
use of debt financing versus pay-as-you-go (or |
|
|
|
| paygo) for capital investment. CBO used related assumptions to
estimate the |
|
|
| average annual spending
to service debt on "old" (that is, pre-2000) |
|
|
|
| investments in drinking
water and wastewater systems; the resulting |
|
|
|
| estimates are common to both of CBO's scenarios but somewhat
lower than |
|
|
| those used in WIN's
analysis. |
|
|
|
|
|
|
| The low-cost case uses a
real interest rate of 3 percent (as does WIN's |
|
|
|
| analysis), and the
high-cost case uses 4 percent. CBO chose those |
|
|
|
| assumptions on the basis
of an estimated 3.2 percent weighted average |
|
|
|
| covering market-rate
bonds and subsidized rates on state revolving fund |
|
|
|
| (SRF) loans. The estimate took into account CBO's long-run
projections for |
|
|
| inflation and the nominal
interest rate on 30-year Treasury bonds, |
|
|
|
| traditional spreads
between Treasuries and municipal bonds, projections of |
|
|
|
| potential assistance from
SRFs, and current interest rates on SRF loans. |
|
|
|
| That range from 3 percent to 4 percent may understate the true
uncertainty |
|
|
| about average interest rates over the 2000-2019 period; however,
once those |
|
|
| figures are combined with
the many other pairs of low-cost and high-cost |
|
|
|
| assumptions, CBO believes that they yield suitably low and high
estimates of |
|
|
| investment spending. |
|
|
|
|
|
|
| CBO assumes the average repayment period on borrowed funds to be
30 years in |
|
|
| the low-cost case and 25 years in the high-cost case; WIN's
analysis assumes |
|
|
| a shorter period of 20 years. Although some (mostly smaller)
municipalities |
|
|
| continue to borrow at
terms as short as 10 years and loans from state |
|
|
|
| revolving funds must still be amortized over no more than 20
years, industry |
|
|
| experts told CBO that water bond maturities have lengthened
overall and that |
|
|
| 30 years is now the standard term. Even within the wastewater
SRF program, |
|
|
| EPA now interprets its
regulations to allow SRFs themselves to borrow |
|
|
|
| 30-year money and use it to buy local systems' debt. As
investment programs |
|
|
| increase, stretching out
debt service will be increasingly important as a |
|
|
|
| way to contain rate increases; indeed, the Boston-area
Massachusetts Water |
|
|
| Resources Authority is
now borrowing 40-year money. Accordingly, CBO |
|
|
|
| considers 30 years a cautiously optimistic assumption for the
average dollar |
|
|
| borrowed over the 2000-2019 period and 25 years an adequately
pessimistic |
|
|
| alternative. |
|
|
|
|
|
|
| Similarly, keeping rates
low in the face of rising investments will also |
|
|
|
| mean reducing the use of paygo financing in favor of borrowed
funds. In two |
|
|
| small 1999 surveys of drinking water and wastewater systems,
indirect data |
|
|
| appear to suggest average
paygo shares of roughly 40 percent and 50 |
|
|
|
| percent.(7) Nonetheless, according to industry experts, systems
undertaking |
|
|
| large amounts of
investment generally use paygo financing very little (often |
|
|
|
| a share of just a few
percent), suggesting that the national average paygo |
|
|
|
| share will fall as
capital spending rises. Reflecting the uncertainty about |
|
|
|
| how quickly and how far
the average will fall through 2019, the high-cost |
|
|
|
| and low-cost cases use
paygo rates of 30 percent and 15 percent, |
|
|
|
| respectively. WIN's
analysis assumes a paygo share of 25 percent. |
|
|
|
|
|
|
| Assumptions about borrowing terms, paygo shares, and interest
rates are also |
|
|
| relevant in estimating
the costs of "old" debt service--that is, the |
|
|
|
| financing costs
associated with previous investments still being paid off |
|
|
|
| during the 2000-2019 period. For simplicity, CBO uses the same
assumptions |
|
|
| about those costs in both scenarios.(8) In particular, CBO
assumes that the |
|
|
| repayment period on funds borrowed before 2000 is 20 years
(shorter than the |
|
|
| 25-year and 30-year periods used going forward) and that the
assumed paygo |
|
|
| shares decline by 1 percent each year, from 50 percent in 1980
to 31 percent |
|
|
| in 1999. The latter
assumption is broadly consistent with the theory that |
|
|
|
| paygo shares decrease as investment programs increase; a higher
trajectory |
|
|
| of paygo rates could have
been justified by the available (limited) survey |
|
|
|
| data, but would have implied larger discontinuities between 1999
and 2000. |
|
|
| Finally, rather than
assume a fixed real interest rate, CBO's analysis used |
|
|
|
| each year's average nominal rate for 10-year Treasuries, reduced
by spreads |
|
|
| ranging from 5 percent to 15 percent between municipal and
Treasury bonds. |
|
|
| CBO then converted total
annual payments for debt service to constant |
|
|
|
| dollars using the gross
domestic product (GDP) deflator. For federal loans |
|
|
|
| through EPA's state revolving funds and the U.S. Department of
Agriculture's |
|
|
| (USDA's) rural utilities
program, the analysis used those same interest |
|
|
|
| rates less 2
percent.(9) |
|
|
|
|
|
|
| The estimates of average
annual costs for "old" debt service resulting from |
|
|
|
| those assumptions are
somewhat lower than WIN's: $4.4 billion instead of |
|
|
|
| $5.1 billion for drinking
water and $4.3 billion instead of $4.4 billion for |
|
|
|
| wastewater.(10) The
differences are primarily attributable to CBO's higher |
|
|
|
| paygo shares and
differences in data sources; the use of variable interest |
|
|
|
| rates and the different
method of converting to real dollars did not have |
|
|
|
| much impact. |
|
|
|
|
|
|
|
| http://www.bankrate.com/brm/rate/dep_ratehome.asp?web=brm&prodtype=dep&state=MD&market=759%2C558&search_from=1&sort=4&no_comments=&product=19&submit=Search |
|
|
|
|
|
|
|
|
| National Savings Rates |
|
Updated as of Thu Oct 21, 01:13PM EST |
|
|
|
|
|
|
| Type |
Rate |
Yield |
|
|
| 3
Mo CD |
1.51% |
1.52% |
|
|
| 6
Mo CD |
1.81% |
1.83% |
|
|
| 1
Yr CD |
2.32% |
2.34% |
|
|
| 2
Yr CD |
2.88% |
2.92% |
|
|
| 2.5 Yr CD |
2.76% |
2.80% |
|
|
| 3
Yr CD |
3.24% |
3.29% |
|
|
| 5
Yr CD |
3.89% |
3.96% |
|
|
|
|
|
| The WSJ listed the Five-year CD ann yield as 4% on 10.19.04, p
C-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|